Change Request Details - CM/22-23/0377
Name of the Supplier SAGAR SPRINGS PRIVATE LIMITED(100186)
Name of the Change Initiator Rushikesh Mehta (SAGAR SPRINGS PVT LTD)
Request Date Oct 16, 2022
Proposal For New Change
Proposed Changes Source change for Raw material
Process Route Change Details
Description of Proposed Change Request to Source for SAE9254 Wire for Outer Coil spring from SAM HWA to TATA STEEL LTD
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1146,1136,1116,HMSI,S1HT03307B,S2HT52107B,
Current Details (Before) Material used was from source SAM HWA
Trigger for the Change Indegeniously available Raw material
Proposed Details (After) Proposed for use of Material from TATA STEEL LTD
Proposed Benefits of the Change Others (Please Specify in Details)
Current Status Inprocess
Status Updated By 851995
Status Update Date Jun 7 2023 5:42PM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Reference FileView File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierSample submission is required with inspection report.Pending1136PlantQA
Assembly trial requiredYesETLIPP lot is required before mass productionPending1136PlantQA
Testing and validation requiredYesSupplierRequired testing like fatigue test and other applicable testing has to be carried out.Pending1136PlantQA
PPAP documents requiredYesSupplierLevel-3 PPAP documents has to be submit.Pending1136PlantQA
Customer approval requiredYesETLDiscussion with customer will be done for sample submission and approvalPending1136PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
PlantQA850826 - Sanjay ShrivastavConcept ApprovedConceptual OK. Sample and required documents has to be submitted from supplier.Nov 22 2022 3:55PM1136
Sourcing856030 - Prasad UpadhyeConcept ApprovedConceptually O.K. Testing & Validation is mandatory before implementationNov 24 2022 1:13PM 
PlantQA851995 - Laxmikant KultheConcept ApprovedRequested change not applicable to ETL K120 Plant.Jun 7 2023 5:42PM1116
PlantQA301380 - Shashank VhangutePending For Conceptual Approval1146
R&D840259 - Vishal PimplePending For Conceptual Approval1146
R&D850719 - Rahul TribhuwanPending For Conceptual Approval1136
R&D850852 - Pramod KulkarniPending For Conceptual Approval1116