Change Request Details - CM/23-24/0433
Name of the Supplier SANJAY TECHNOPLAST PVT.LTD.(100827)
Name of the Change Initiator Ashutosh Upreti
Request Date May 15, 2023
Proposal For New Change
Proposed Changes Change in location
Process Route Change Details
Description of Proposed Change Part obsolete at Waluj location, Hence Tool move from waluj to Pantnagar
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1126,BAL,S2MF07102B,
Current Details (Before) Part Supply from our STPPL Waluj Plant
Trigger for the Change Part Obsolete
Proposed Details (After) Part Manufacturing at STPL Pantnagar
Proposed Benefits of the Change Others (Please Specify in Details)
Current Status Concept Approved
Status Updated By 301640
Status Update Date Jun 6 2023 11:38AM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Reference FileView File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierPending1126PlantQA
Assembly trial requiredYesSupplierPending1126PlantQA
Testing and validation requiredYesSupplierPending1126PlantQA
PPAP documents requiredYesSupplierPending1126PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
PlantQA700254 - Dinesh DeConcept ApprovedConceptually OK. But need flow CMR procedure before run the die in production.May 20 2023 9:41AM1126
SQA302090 - Atul KhocheConcept ApprovedConceptually approved, subjected to PPAP approval from Plant QA.May 23 2023 9:48AM 
Sourcing301640 - Shrikant MuleyConcept ApprovedConceptually approved, subjected to PPAP approval from Plant QAJun 6 2023 11:38AM