Change Request Details - CM/23-24/0536
Name of the Supplier SHARP ENGINEERS.(100106)
Name of the Change Initiator M/s Sharp Engineers.
Request Date Jan 16, 2024
Proposal For New Change
Proposed Changes Change in process parameters /Process flow sequence, Outsourcing /Sub Supplier Change, Manufacturing process route change
Process Route Change Details Process route changed from traub machining to cold forge machining.
Description of Proposed Change Cold forge machining for FORK BOLT - UG 4.5 (550DZ04702)
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1126,1117,BAL,550DZ04702,NA
Current Details (Before) Traub route machining ( After RM inward parting & drilling on trub machine then CNC process.
Trigger for the Change To improve quality of the product at Hex punch.
Proposed Details (After) Cold forge machining (After RM inward & inspection cod forging is being done then CNC machining and other process.
Proposed Benefits of the Change Quality Improvement
Current Status Inprocess
Status Updated By 301640
Status Update Date May 8 2024 2:52PM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Proposed Details (After)View File
Current Details (Before)View File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierPending1117PlantQA
Assembly trial requiredYesETLPending1117PlantQA
Testing and validation requiredYesETLPending1117PlantQA
PPAP documents requiredYesSupplierPending1117PlantQA
Samples requiredYesSupplierPending1126PlantQA
Assembly trial requiredYesSupplierPending1126PlantQA
Testing and validation requiredYesSupplierPending1126PlantQA
PPAP documents requiredYesSupplierPending1126PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
PlantQA855273 - Rajkumar MaindarkarConcept ApprovedProcess audit to be conducted along with SQAFeb 6 2024 4:52PM1117
PlantQA700254 - Dinesh DeConcept ApprovedConceptually OK, but need PAPP approval through complete audit i.e. system, process & product audit by ETLFeb 26 2024 3:09PM1126
SQA302090 - Atul KhocheConcept ApprovedConceptually approved - Subjected to successful completion of ETL CFT audit at forging supplier and samples approval from Plant QA.Mar 5 2024 9:49AM 
Sourcing301640 - Shrikant MuleyConcept ApprovedConceptually Approve as Q improvement. Please go ahead as per our regular process.May 8 2024 2:52PM 
R&D850852 - Pramod KulkarniPending For Conceptual Approval1117