Change Request Details - CM/23-24/0565
Name of the Supplier SR AUTO PARTS UNIT II(101001)
Name of the Change Initiator Maharudra Kokate
Request Date Mar 12, 2024
Proposal For New Change
Proposed Changes Change in location
Process Route Change Details
Description of Proposed Change We are going to shift the manufacturing facilities to our internal Plant.
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1132,PIAGGIO,1610400201,520FG13802,520FG14102,C30400401B,C30400501B,
Current Details (Before) We are manufacturing the parts in Unit-2 S-94, MIDC Bhosari, Pune-4111026
Trigger for the Change Location change to improve the material handling.
Proposed Details (After) We want to shift the manufacturing setup in Unit-3 J142/143, MIDC Bhosari, Pune-411026
Proposed Benefits of the Change Material Handling Improvement
Current Status Concept Approved
Status Updated By 301640
Status Update Date Jun 27 2024 4:49PM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Reference FileView File
Reference FileView File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierPending1132PlantQA
Assembly trial requiredYesETLPending1132PlantQA
Testing and validation requiredYesETLPending1132PlantQA
PPAP documents requiredYesSupplierPending1132PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
PlantQA841004 - Sandeep GarudConcept ApprovedSystem Audit RE PPAP requiredJun 17 2024 5:43PM1132
Sourcing301640 - Shrikant MuleyConcept ApprovedConceptually approved subject to successfully completion of ETL Audit & & required testing and validation by ETL R & D and Plant QA.Jun 27 2024 4:49PM