Change Request Details - CM/24-25/0584
Name of the Supplier METAFORGE ENGG.(I) PVT.LTD.(100049)
Name of the Change Initiator Adarsh Aher
Request Date Apr 23, 2024
Proposal For New Change
Proposed Changes Change in location
Process Route Change Details
Description of Proposed Change Manufacturing location change Plant-1 Mhasrul to Plant-2 Khatwad
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1135,1132,BAL,HMSI,HERO,YAMAHA,REML,PIAGGIO,520FK00102,520FK00302,520KS00102,520KS00502,520KS01002,520KS01102,520KS02102,520KS02702,520KS03602,520KS03802,C2KS02402B,C3KS00202B,No
Current Details (Before) We are doing Rivet family Cold forging in Plant -1 Mhasrul Nashik
Trigger for the Change Plant-2 Expansion
Proposed Details (After) Shift the Rivet family Cold forging machines in Plant -2 Khatwad Nashik
Proposed Benefits of the Change Productivity Improvement
Current Status Concept Approved
Status Updated By 841004
Status Update Date Jun 17 2024 5:25PM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Reference FileView File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierPending1135PlantQA
Testing and validation requiredYesSupplierPending1135PlantQA
PPAP documents requiredYesSupplierPending1135PlantQA
Samples requiredYesSupplierPending1132PlantQA
Assembly trial requiredYesETLPending1132PlantQA
Testing and validation requiredYesETLPending1132PlantQA
PPAP documents requiredYesSupplierPending1132PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
Sourcing301640 - Shrikant MuleyConcept ApprovedConceptually Approve . Please go ahead as per our regular process.May 8 2024 2:41PM 
PlantQA700254 - Dinesh DeConcept ApprovedConceptually 0K, need sample with all test reports & PPAP file because manufacturing facility change.May 11 2024 10:49AM1135
SQA854396 - Amit BhaleraoConcept Approvedfacility audit and PPAP to be followedJun 13 2024 11:40AM 
PlantQA841004 - Sandeep GarudConcept ApprovedSample to be submitted System Audit and PPAP Audit to be planned at New plantJun 17 2024 5:25PM1132