Change Request Details - CM/24-25/0622
Name of the Supplier SAPTAGIRI ENGINEERING PRIVATE LIMIT(101273)
Name of the Change Initiator Saptagiri Engineering Pvt. Ltd.
Request Date Sep 13, 2024
Proposal For New Change
Proposed Changes Change in location
Process Route Change Details
Description of Proposed Change Powder coating supplier ( Shri Samarth Enterprises ) Location change for few parts. From Shri Samarth Enterprises to Shri Samarth Surface Coat LLP
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
1143,1136,1126,1120,1118,1117,1116,BAL,HMSI,HERO,13DF01307,520BG07202,530DA00507,530DA00703,530PL00412,533PL00207,550FU01902,S2DA03907B,S2DF01007B,NA
Current Details (Before) Shri Samarth Enterprises ( Plot No W-28 , MIDC , Industrial Area waluj, Aurangabad )
Trigger for the Change Lack of Space
Proposed Details (After) Shri Samarth Surface Coat LLP (Plot No A-6 MIDC, Industrial Area,Waluj , Aurangabad.
Proposed Benefits of the Change Others (Please Specify in Details)
Current Status Concept Rejected
Status Updated By 854881
Status Update Date Nov 19 2024 3:52PM
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
File For File Name
Proposed Details (After)View File
Activities For Final Approval
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
Samples requiredYesSupplierPending1117PlantQA
Assembly trial requiredYesETLPending1117PlantQA
Testing and validation requiredYesETLPending1117PlantQA
PPAP documents requiredYesSupplierPending1117PlantQA
Samples requiredYesSupplierPending1118PlantQA
Assembly trial requiredYesETLPending1118PlantQA
Testing and validation requiredYesSupplierPending1118PlantQA
PPAP documents requiredYesSupplierPending1118PlantQA
Customer approval requiredYesETLPending1118PlantQA
Samples requiredYesSupplierPending1136PlantQA
Assembly trial requiredYesETLPending1136PlantQA
Testing and validation requiredYesSupplierPending1136PlantQA
PPAP documents requiredYesSupplierPending1136PlantQA
Customer approval requiredYesETLPending1136PlantQA
Samples requiredYesSupplierPending1126PlantQA
Testing and validation requiredYesSupplierPending1126PlantQA
PPAP documents requiredYesSupplierPending1126PlantQA
Samples requiredYesSupplierPending1116PlantQA
Assembly trial requiredYesETLPending1116PlantQA
Testing and validation requiredYesSupplierPending1116PlantQA
PPAP documents requiredYesSupplierPending1116PlantQA
Customer approval requiredYesETLPending1116PlantQA
 
Approval Process History
Role Employee Request Status Comments Updated On Status
SQA302090 - Atul KhocheConcept ApprovedConceptually approved p subjected to sample validation and approval by Plant QAOct 8 2024 11:05AM 
Sourcing301640 - Shrikant MuleyConcept ApprovedConceptually approved - subjected to samples ETL approval from SQA & QAOct 8 2024 5:07PM 
PlantQA855273 - Rajkumar MaindarkarConcept ApprovedConceptually approved - Need to do Process audit through SQA. Required all testing reports in line with customer requirements.Oct 16 2024 4:27PM1117
PlantQA852974 - Yash Pal SinghConcept ApprovedPLS SUBMITT SAMPLE FOR OUR TESTING ALONG WITH PPAP DOCUMENTS . AFTER CUSTOMER APPROVEL SUPPLY CAN START.Oct 17 2024 3:10PM1118
PlantQA850826 - Sanjay ShrivastavConcept ApprovedETL QAV needs to clear. Sample with PPAP document is required. After sample approval, customer approval for mass production supply can be started.Oct 20 2024 2:23PM1136
PlantQA700254 - Dinesh DeConcept ApprovedConceptually ok. Need to do Process audit through SQA and required all testing approval before submission sample.Nov 6 2024 4:29PM1126
PlantQA851995 - Laxmikant KultheConcept ApprovedConceptually ok. Need to do Process audit through SQA and required all testing approval before submission sampleNov 7 2024 12:44PM1116
PlantQA854881 - Omprakash SunkawarConcept RejectedThis is not related plant 1120Nov 19 2024 3:52PM1120
PlantQA402220 - Lekhraj .Pending For Conceptual Approval1143
PlantQA855352 - Ravi NawkarPending For Conceptual Approval1120