Change Request Details - FT/PUR-SQA/99
Name of the Supplier HELICAL SPRINGS(100185)
Name of the Change Initiator Harish Chander
Request Date Mar 11, 2020
Proposal For 1
Proposed Changes Change in Layout, Addition/Deletion of process stage
Process Route Change Details
Description of Proposed Change Layout Change
Part Details related with change
ETL Plant Customer Part No. Proposed Saving
530HT012070
013HT093070
013HT094070
S2HT12007B0
S2HT11807B0
S2HT11707B0
S2HT28407B0
013HT098070
S2HT13007B0
533HT027070
S1HT03307B0
S2HT31507B0
S2HT40307B0
533HT075070
533HT074070
S2HT34407B0
S2HT23307B0
Current Details (Before) Process wise layout, i.e. Coiling done in coiling section, Stress relieving done in stress relieving section, grinding done in grinding section and so on. Material moves in batches.
Trigger for the Change Quality Improvement
Proposed Details (After) Product Line Layout, i.e. all processes / machines set in a line. The product moves from one machine to other through conveyer
Proposed Benefits of the Change System Improvement
Current Status Approved & Closed
Status Updated By
Status Update Date
Implementation Plan
-------
Activity Target Date Responsibility Status
Reference Files
-------
File For File Name
Activities For Final Approval
-------
Activity Answer Responsibility ETL Remarks Supplier's Remarks Final Remarks Status Plant Department
 
Approval Process History
-------
Role Employee Request Status Comments Updated On Status