Request No. - CAR01620
Contractor Assessment Request Details
Assessment Type New
Vendor
Contractor Anjanadri
Contractor Location Malur
Contractor Email ID Anjanadri
Plant Code 1146
 
Preliminary Details For Evaluation
Contractor Type Civil Fabrication
Name of Company / Contractor ANJANADRI CIVIL CONTRACTOR
Contact Person Name ARUN KUMAR A.G
Contact Number 9964639292
Work Description CIVIL WORK, ELECTRICAL, PLUMBING, PAINTING, FABRICATION, ALUMINUM, UPVC, WOOD WORK.
Previous ETL Contracts YES
Existing Clientele JBM GROUP, ASK AUTOMOBILES UNIT VIII, ASK AUTOMOBILES UNIT II , TS INTERSETS INDIA PRIVATE LIMITED, ADVIK - HI - TECH PVT. LTD.
Organizational Chart 1620_OrganizationalChart_.pdf
Employees Head Count 10
Employees Deployed Count at ETL 8
Supervisors Count 1
Is Sub Contractor Nominated ? Yes
Sub Contractor PRM ENTERPRISES
Contractors Financial Health & Capability (Turnover in INR) 8000000
C A Certificate 1620_CACertificate_.pdf
Does your last two years balance sheet shows profit? Yes
Balance Sheet 1620_BalanceSheet_.pdf
Do you have at least 3 years of experience for carrying out similar activity? No
Experience Certificate
 
Section 1 - Mandatory Requirement
Sr.No Requirement Text Options License / Registration No. / Policy No. Attachment Valid Till Score
1License under the Factory Act.1948 / Contract Labor Act / Shop ActCompliedMal/MAL/CE/0001/20171620_11__section1_.pdf31.12.20265
2Number of employees authorized to deploy as per licenseComplied191620_12__section1_.pdf31.12.20265
3Is the organization registered for EPF?CompliedPYKRP31742220001620_13__section1_.pdf31.12.20265
4Is the organization registered for ESIC?Complied530004591700010191620_14__section1_.pdf05.12.20235
5Is the organization registered for GSTN?Complied29BPCPA2723N1ZW1620_15__section1_.pdf31.12.20265
6Workmen compensation Policy / Group InsuranceComplied432878831620_16__section1_.pdf31.12.20265
7Are workers working hours complied with the current applicable law in the country?CompliedMal/MAL/CE/001/20171620_17__section1_.pdf31.12.20265
8Are wages paid on the basis of Minimum Wages Act?CompliedMal/MAL/CE/001/20171620_18__section1_.pdf31.12.20265
9Licensed Electrical Supervisor / Electrician If Applicable (For Electrical Work)Not Applicable5
10Any complaint registered against the contractor in past under Labour lawsNot Applicable5
 
Total - 50
 
Section 2 - Safety Performance
Sr.No Requirement Text Answer Details Attachment Score
1No. of Accidents (Medical Treatment) in last 2 years05
2No. of Fatalities (Verify from Govt. data / reference check)05
3No. of Lost time injuries as per Factories Act 1948 (Injured person not able to work more than 48 hours from time of accident)05
4No. of Fire Incident in last 2 years05
5Has the organisation been prosecuted for an HSE breach or injury to an employee? Specify nos.05
 
Total - 25
 
Section 3 - General EHS Systems
Sr.No Requirement Text Answer Details Attachment Score
1HSE Policy (Provide evidence by supplying copies of relevant documents)Not Applicable5
2Induction and Training (provide relevant documents)Yes1620_27__section3_.pdf5
3PPE’s maintained in Good ConditionYes1620_28__section3_.pdf5
4Health monitoring of Employees - Medical Check Up Done for employee’s as per Form 7 (date / Fitness Certificate from AFIH doctor)Not Applicable5
5Does the organization regularly inspect and maintain hand tools, machinery (cranes, vehicles, hoists/lifting tools, etc.)Yes1620_30__section3_.pdf5
 
Total - 25
 
Section 4 - EHS Practices
Sr.No Requirement Text Answer Details Attachment Score
1Is the organization aware of Method Statement/ Method Statement Adherence?Yes5
2Are the contract employees aware of Emergency Response Procedure?Yes5
3Has the organization conducted a HIRA study in past / or as a part of current practice?Yes5
4Does the organization have and follow safe work procedures, documents which define how risks relevant to the contracted activities are managed?Yes5
5Is the contract employee aware of Work Permit System / Work Permit Adherence?Yes5
 
Total - 25
 
Section 5 - Plant and Equipment
Sr.No Requirement Text Answer Details Attachment Score
1Are the tools and equipment used in good working condition?Yes1620_36__section5_.pdf5
2Do the tools and equipment comply with standards such as ISI Mark / Energy Efficient 5 star rating guidelines?Yes5
3Is the holding handle of equipment in good condition?Yes5
4Are all plants and equipment compliant with the safety requirements? (including not damaged cables, no loose connections, equipped with 3 pin top)Yes5
5Do contract employees have correct licenses / certificates to operate the plants and equipment?Yes5
 
Total - 25
 
Total Score
Section Score
Section 1
Mandetory Requirement
50
Section 2
Safety Performance & System Awareness
25
Section 3
General EHS Systems
25
Section 4
EHS Practices
25
Section 5
Plant and Equipment
25
Total Score
150
 
The overall ranking of pre-qualification is 100 % (Professional)
 
 
Approval Process History
Role Employee Request Status Comments Updated On
Department Head400452 - Mathan SurulivelApprovedOkDec 5 2023 4:21PM
EHS401800 - Ravindran NApprovedok for Civil workDec 5 2023 4:33PM
HR400601 - Girish GunagiApprovedDear sir, As discussed ok for Civil vendorDec 5 2023 4:51PM
CorporateEHS400326 - Sunil SonarResendEPF is mandatoryDec 7 2023 5:59PM
CorporateEHS400326 - Sunil SonarApprovedOK ApprovedJan 9 2024 4:03PM
HeadIR855987 - Kalyan PawarApprovedApprovedJan 11 2024 5:10PM