QFR No - 7000828629
Defect Details
NC No. | 7000828629 |
NC Date | 29/03/2022 |
NC Submission Date | |
Part No. | F2DZ08810B |
Part Name | K0PG FORK BOLT |
Supplier Name & Code | 100189-SANGKAJ STEEL PVT LTD. |
ETL Plant | 1136-ETL Suspension Sanand |
Defect Details | DIMN.U/SIZE.-Grove Dia Over Size |
1. Problem Description
Defect Description | Critical dimension Groove Under Size i.e. 22.23, 22.29, 22.30 again the spec of 22.45-0.1 Also observed Packing standard failure as well as heavy dent and damage at parts |
Detection Stage | Receipt |
Problem Severity | Function |
NG Quantity | 2000 |
Is Defect Repeatative? | No |
Defect Sketch / Photo |
Supplier Communication Details
Quality Head Email ID | maheshmishra@sangkaj.com |
Plant Head/CEO Email ID | steel@sangkaj.com |
MD Email ID | anirudh.2007@hotmail.com |
2. Stock Details & action taken for NG parts
Location | ETL End | Warehouse | Transit | Supplier FG | Supplier WIP | Total |
---|---|---|---|---|---|---|
Total Qty |
0
|
0
|
0
|
2000
|
2000
|
4000
|
Check Qty |
0
|
0
|
0
|
2000
|
2000
|
4000
|
NG Qty |
0
|
0
|
0
|
0
|
0
|
0
|
Scrap | 0 |
Rework | 0 |
Under Deviation | 0 |
Containment Action |
---|
100% material we inspect with DVC |
3. Process Flow
Process Flow Description |
---|
Inward RM - Parting - CNC st - CNC 2nd - Plating - final inspection -Dispatch |
4. Process Details
Process / Operation | CNC |
Outsource | No |
Machine / Cell | CNC cell |
Machine / Cell No. | 38 |
5. Problem Analysis
Type | Possible Cause | Fact Verification | Jud |
---|---|---|---|
Method | insert plunge 2 time in groove | found not ok | X |
Man | New manpower | Old manpower found ok | O |
6. Inspection Method Analysis (Current)
Inspection Method | Gauge |
Other Inspection Method | |
Check Point at Final Inspection | Yes |
Checking Freq. | Sampling |
Sampling | No |
Sample Size | 50 |
7. Root Cause Analysis (Occurance)
Why 1 | OD oversize observed in KOPG 22.45mm |
Why 2 | Insert plunge 2 times |
Why 3 | Standard insert is not available. |
Why 4 | |
Why 5 | |
Root Cause (Occurance) | Standard insert is not available. |
Root Cause Analysis (Outflow)
Why 1 | OD oversize observed in KOPG 22.45mm |
Why 2 | Skip from inspection |
Why 3 | Sampling inspection |
Why 4 | |
Why 5 | |
Root Cause (Outflow) | Sampling inspection |
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type | Countermeasure Details | Responsibility | Target Date | Actual Date | Status |
---|---|---|---|---|---|
Outflow | 100% material inspect with DVC | Mahesh Mishra | 20/04/2022 | 21/04/2022 | Pending |
9. Inspection Method After Customer Complaint
Change In Inspection System | Yes |
Change Details | 100% material inspect with DVC instead of snap gauge. |
Inspection Method | Instrument |
Other Inspection Method | |
Check Point at Final Inspection | Yes |
Checking Freq. | 100% |
Sampling | No |
Sample Size | 00 |
10. Evidance of Countermeasure
Occurance (Before) |
|
Occurance (After) |
|
Outflow (Before) |
|
Outflow (After) |
|
11. Horizontal Deployment
Horizontal Deployment Required | |
Applicable Machine / Model / Plant |
12. Document Review
Documents | |
Specify Other Document |
13. Effectiveness Of Action
Reviewed Quantity | |
Reason for submission |