QFR No - 8000787196
Defect Details
NC No. 8000787196
NC Date 11/05/2022
NC Submission Date
Part No. 520FW04702
Part Name CLUTCH HOUSING FULL FINISHED-K70
Supplier Name & Code 100656-MADHURA DIE CAST PVT.LTD
ETL Plant 1132-ETL K-226/1 TRANSMISSION
Defect Details OPERATION MISSING-2ND SETUP M/C OPERATION MISSING
 
1. Problem Description
Defect Description 2ND SETUP MACHINING OPERATION MISSING
Detection Stage Inprocess
Problem Severity Fitment
NG Quantity 1
Is Defect Repeatative? No
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID madhuradiecast@gmail.com
Plant Head/CEO Email ID madhuradiecast@gmail.com
MD Email ID madhuradiecast@gaikegroup.in
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
2000
0
0
2500
1500
6000
Check Qty
2000
0
0
0
0
2000
NG Qty
1
0
0
0
0
1
 
Scrap 1
Rework 0
Under Deviation 0
Containment Action
1.100% Stock segregate at customer end and Supplier end stock.
 
3. Process Flow
Process Flow Description
1.Casting 2.fetling 3. CNC 1st Set-up 4.CNC 2nd Set-up 5.Final Inspection
 
4. Process Details
Process / Operation CNC 2nd Set-up
Outsource No
Machine / Cell JE/CNC NO.02
Machine / Cell No. JE/CNC NO.02
5. Problem Analysis
Type Possible Cause Fact Verification Jud
MaterialComponent was skipped from 2nd side Cnc operationverify and checked found okO
ManUnskill operator loading the vechicleverify found not okX
MethodComponent was mix up on loading stageLoading person not aware about part operationX
 
6. Inspection Method Analysis (Current)
Inspection Method Other
Other Inspection Method 100% Visual checking
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
7. Root Cause Analysis (Occurance)
Why 1 2nd side missing component was a mix-up with ok component
Why 2 Vehicle loading operator is was put not ok component to ok bin because one component is required for fulfilling the bin
Why 3
Why 4
Why 5
Root Cause (Occurance) The vehicle loading operator was put not ok component to the ok bin because one component is required for fulfilling the bin.
 
Root Cause Analysis (Outflow)
Why 1 Final inspector not put tag in ok component bin
Why 2 Unskill inspector
Why 3
Why 4
Why 5
Root Cause (Outflow) Unskill inspector
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
Occurance1. Awareness was created about the defect in the Loading operator. 2. Don`t put the component ready for the dispatch bin without the permission of the dispatch supervisor. 3. Ready for dispatch tag put in the bin for confirmation of ok part for dispatch.Dispatch Supervisior15/05/202216/05/2022Completed
Outflow1. Training and awareness are given to the final inspector. 2. Cross verify by Dispatch component by the inspector before loading the vehicle.QA Engineer12/05/202213/05/2022Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details Cross verify by Dispatch component by the inspector before loading the vehicle.
Inspection Method Other
Other Inspection Method Visual
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
10. Evidance of Countermeasure
Occurance (Before) The vehicle loading operator was put not ok component to the ok bin because one component is required for fulfilling the bin.
106_Occurance_Before.jpeg
Occurance (After) 1. Awareness was created about the defect in the Loading operator. 2. Don`t put the component ready for the dispatch bin without the permission of the dispatch supervisor. 3. Ready for dispatch tag put in the bin for confirmation of ok part for dispatch.
106_Occurance_After.pdf
Outflow (Before) Final inspector not put tag in ok component bin
106_Outflow_Before.jpeg
Outflow (After) 1. Training and awareness are given to the final inspector. 2. Cross verify by Dispatch component by the inspector before loading the vehicle.
106_Outflow_After.pdf
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant ALL ETL COMPONENT
 
12. Document Review
Documents PFMEA, InspCheckSheet
Specify Other Document QA OPL
 
13. Effectiveness Of Action
Reviewed Quantity 1000
Reason for submission Analysis not proper