QFR No - 8000788627
Defect Details
NC No. 8000788627
NC Date 24/05/2022
NC Submission Date
Part No. 161FW00233
Part Name HOUSING CLUTCH DISCOVER 100CC
Supplier Name & Code 200990-OM MAHABALI ENTERPRISES
ETL Plant 1132-ETL K-226/1 TRANSMISSION
Defect Details DIAMETER OVER SIZE- DIA O/S UP TO 36.03MM AG.35.966/.991MM
 
1. Problem Description
Defect Description OD Ø36 -0.009/-0.034 mm found Oversize up to 27~42 Micron
Detection Stage Inprocess
Problem Severity Fitment
NG Quantity 4
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID info@ommahabali.com
Plant Head/CEO Email ID info@ommahabali.com
MD Email ID om.mahabali208@gmail.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
1500
0
0
680
366
2546
Check Qty
1500
0
0
680
366
2546
NG Qty
4
0
0
0
0
4
 
Scrap 4
Rework 0
Under Deviation 0
Containment Action
Boss OD 100 % Inspection By Air Plug gauge With Marking at Part Right Mark
 
3. Process Flow
Process Flow Description
CNC Operation
 
4. Process Details
Process / Operation CNC Operation
Outsource No
Machine / Cell CNC
Machine / Cell No. 06
5. Problem Analysis
Type Possible Cause Fact Verification Jud
Tool3.0 mm PCD Insert Cornar damge3.0 mm PCD Insert Cornar damgeO
 
6. Inspection Method Analysis (Current)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100 %
7. Root Cause Analysis (Occurance)
Why 1 Boss OD Over size
Why 2 Due to PCD 3.0 mm Grooving Insert Minor Corner damage
Why 3 Due to Major Interruption in 3 Boss Face
Why 4
Why 5
Root Cause (Occurance) PCD Insert changed
 
Root Cause Analysis (Outflow)
Why 1 Frequency of Boss OD inspection 100% Inspection By Air Ring Gauge.
Why 2 No Making on parts for Boss OD inspection.
Why 3
Why 4
Why 5
Root Cause (Outflow) started 100 % Boss OD Inspection By Air Ring Gauge with Date & Shift
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccurancePCD Insert should be changeMr. Thute.a27/05/202226/05/2022Completed
OutflowBoss OD inspection 100% Inspection By Air Ring Gauge.Mr.Shahare.s27/05/202226/05/2022Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details started 100 % Boss OD Inspection By Air Ring Gauge with Date & Shift
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) 3 mm PCD Insert Corner damage
142_Occurance_Before.jpg
Occurance (After) 3 mm PCD Insert should be chnage
142_Occurance_After.jpg
Outflow (Before) 100 % Insertion By Air Ring Gauge with Marking Right Put in Part
142_Outflow_Before.jpg
Outflow (After) Started Boss OD 100 % Inspection By Air Ring gauge With Making Date and Shift put in Puart
142_Outflow_After.jpg
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant CNC Machine
 
12. Document Review
Documents ControlPlan, InspCheckSheet
Specify Other Document No
 
13. Effectiveness Of Action
Reviewed Quantity 2000
Reason for submission OK