QFR No - 8000790797
Defect Details
NC No. 8000790797
NC Date 10/06/2022
NC Submission Date
Part No. F1DZ00902B
Part Name FORK BOLT K86A
Supplier Name & Code 100189-SANGKAJ STEEL PVT LTD.
ETL Plant 1146-ETL Suspension Narasapura
Defect Details OIL LEAKAGE-OIL LEAKAGE DUE TO FORK BOLT CENTER HOLE
 
1. Problem Description
Defect Description K0YA Fort fork oil leakage through fork bolt compliant came from HMSI -3F because K86 fork bolt center hole available
Detection Stage Customer End
Problem Severity Function
NG Quantity 1
Is Defect Repeatative? No
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID maheshmishra@sangkaj.com
Plant Head/CEO Email ID pardeshinr@sangkaj.com
MD Email ID anirudh.2007@hotmail.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
5000
0
0
2300
0
7300
Check Qty
5000
0
0
2300
0
7300
NG Qty
1
0
0
0
0
1
 
Scrap 1
Rework 0
Under Deviation 0
Containment Action
All pipeline material 100% sagrigated and material keep aside for with identification marking.
 
3. Process Flow
Process Flow Description
1.RM INWARD & INSPECTION - 2.TRAUB MACHINE CUTTING AND DRILL - 3.CNC 1ST SETUP - 4.CNC 2ND SETUP - 5.ACROSS FLAT MILLING - 6.DEBURRING - 7. PLATING -8.FINAL INSPECTION -9.DISPATCH
 
4. Process Details
Process / Operation TRAUB MACHINING
Outsource No
Machine / Cell TRAUB SECTION
Machine / Cell No. 52
5. Problem Analysis
Type Possible Cause Fact Verification Jud
MachineMachine condition is not okMachine condition is ok daily check sheet verifiedO
ManNew manpowerOperator skilled and skill matrix verified.O
ManNew operatorOperator is oldO
ManNot aware about processManpower aware about processO
MachineAdjustment nut worn out & LooseAdjustment nut worn out & Loose FoundX
MachineMachine is not in workingMachine is in working conditionO
MethodWrong judgment during visualJudgement is wrong because marking is provided on centre of the fork boltX
MaterialRM DamagesMaterial checked and found okO
MethodWrong trainingCorrect training is providedO
 
6. Inspection Method Analysis (Current)
Inspection Method Other
Other Inspection Method Visual inspection
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100
7. Root Cause Analysis (Occurance)
Why 1 Through hole observed in Fork Bolt K-86
Why 2 Excess depth of material cut
Why 3 Drill travels more than its limit.
Why 4 Adjustment nut of stopper was loose
Why 5 Adjustment nut worn out
Root Cause (Occurance) Adjustment nut worn out
 
Root Cause Analysis (Outflow)
Why 1 Through hole observed in Fork Bolt K-86
Why 2 Skipped from final inspector during inspection
Why 3 Judgement is wrong because marking is provided on center of the fork bolt.
Why 4
Why 5
Root Cause (Outflow) Judgement is wrong because marking is provided on center of the fork bolt.
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccuranceStopper Adjustment nut replaced with new one.Mr. Raut santosh13/06/202213/06/2022Completed
OccuranceStopper double lock nut used for tightening.Mr. Raut santosh13/06/202213/06/2022Completed
OutflowSkip from inspection due to wrong judgment so awareness given to inspector.Shende P10/06/202213/06/2022Completed
OccuranceStep drill used at semi finish stage to maintain drill depth sizeMr. Raut santosh11/06/202213/06/2022Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System No
Change Details NA
Inspection Method Other
Other Inspection Method Visual inspection
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100
10. Evidance of Countermeasure
Occurance (Before) Adjustment nut worn out
169_Occurance_Before.pptx
Occurance (After) Stopper double lock nut used for tightening.
169_Occurance_After.pptx
Outflow (Before) Judgement is wrong because marking is provided on centre of the fork bolt .
169_Outflow_Before.xlsx
Outflow (After) Skip from inspection due to wrong judgment so awareness given to inspector.
169_Outflow_After.xlsx
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant NA
 
12. Document Review
Documents ControlPlan, PMCheckSheet, WISOP, InspCheckSheet
Specify Other Document NA
 
13. Effectiveness Of Action
Reviewed Quantity
Reason for submission