QFR No - 8000814841
Defect Details
NC No. | 8000814841 |
NC Date | 20/12/2022 |
NC Submission Date | |
Part No. | F2FA21433M |
Part Name | FORK PIPE MACHINED (K17A FF) |
Supplier Name & Code | 101024-TUBE INVESTMENTS OF INDIA LTD |
ETL Plant | 1126-ETL Pantnagar |
Defect Details | DEPTH U/SIZE.-CAULKING DEPTH UNDER SIZE |
1. Problem Description
Defect Description | Caulking depth under size in fork pipe K17 |
Detection Stage | Inprocess |
Problem Severity | Fitment |
NG Quantity | 235 |
Is Defect Repeatative? | No |
Defect Sketch / Photo |
Supplier Communication Details
Quality Head Email ID | AmitVD@tii.murugappa.com |
Plant Head/CEO Email ID | guptaajay@tii.murugappa.com |
MD Email ID | mukeshahuja@tii.murugappa.com |
2. Stock Details & action taken for NG parts
Location | ETL End | Warehouse | Transit | Supplier FG | Supplier WIP | Total |
---|---|---|---|---|---|---|
Total Qty |
2500
|
2000
|
0
|
0
|
0
|
4500
|
Check Qty |
2500
|
2000
|
0
|
0
|
0
|
4500
|
NG Qty |
235
|
5
|
0
|
0
|
0
|
240
|
Scrap | 240 |
Rework | 0 |
Under Deviation | 0 |
Containment Action |
---|
100% segregation done at customer end & 100% segregation done at warehouse |
3. Process Flow
Process Flow Description |
---|
1. Parting 2. CNC Machining First 3. CNC Machining 2nd 4. Drilling |
4. Process Details
Process / Operation | Machining & Drilling |
Outsource | No |
Machine / Cell | MACHINE SHOP |
Machine / Cell No. | CNC MACHINE -01 |
5. Problem Analysis
Type | Possible Cause | Fact Verification | Jud |
---|---|---|---|
Method | Inspection Instruments & Lux Level | Inspection with DPG, Lux level- 620 | O |
Man | Operator | Untrained operator given Wrong offset in Programme | X |
Material | Tube Id & Machining Margin | As per Specs. | O |
Tool | Temperature & Humidity | No Issue | O |
Machine | CNC Programme execution | Programme not Locked | X |
6. Inspection Method Analysis (Current)
Inspection Method | Gauge |
Other Inspection Method | |
Check Point at Final Inspection | No |
Checking Freq. | 100% |
Sampling | No |
Sample Size | 5 |
7. Root Cause Analysis (Occurance)
Why 1 | Fork Pipe Caulking Depth Undersize |
Why 2 | Depth Less maintained during CNC Machining |
Why 3 | Due to wrong offset given in the Programme by operator |
Why 4 | Programme was not Locked |
Why 5 | |
Root Cause (Occurance) | Operator was Untrained and CNC programme was not Locked, Due to Which wrong offset given in Programme by the Operator. |
Root Cause Analysis (Outflow)
Why 1 | Fork Pipe Caulking Depth Undersize Part received at Customer end |
Why 2 | Caulking Depth Inspection done on sampling basis. |
Why 3 | 100% Inspection not defined in the WI |
Why 4 | Because This type of defect not reported in past |
Why 5 | |
Root Cause (Outflow) | This Parameter was checking on Sampling basis, because This type of defect not reported in past. |
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type | Countermeasure Details | Responsibility | Target Date | Actual Date | Status |
---|---|---|---|---|---|
Occurance | 1. CNC Programme Locked 2. Only Production Supervisor will give the offset. 3. After any correction Quality Line Inspector will recheck the parts and provide approval. | TANVEER | 16/12/2022 | 15/12/2022 | Completed |
Outflow | 1. After every 50Parts, operator will check this parameter with Attribute Gauge. 2. 100% Inspection Started at PDI Stage. | TANVEER | 16/12/2022 | 15/12/2022 | Completed |
9. Inspection Method After Customer Complaint
Change In Inspection System | Yes |
Change Details | 100% Inspection started at PDI Stage |
Inspection Method | Gauge |
Other Inspection Method | |
Check Point at Final Inspection | Yes |
Checking Freq. | 100% |
Sampling | No |
Sample Size | 100% |
10. Evidance of Countermeasure
Occurance (Before) |
CNC Programme Not Locked 323_Occurance_Before.jpeg |
Occurance (After) |
CNC Programme Locked 323_Occurance_After.jpeg |
Outflow (Before) |
After every 50 Parts, operator will check this parameter with Attribute Gauge.ONLY BASIC TRAINING GIVEN 323_Outflow_Before.jpg |
Outflow (After) |
100% Inspection Started at PDI Stage. 323_Outflow_After.jpg |
11. Horizontal Deployment
Horizontal Deployment Required | Yes |
Applicable Machine / Model / Plant | All Models |
12. Document Review
Documents | ControlPlan, PFMEA, WISOP, InspCheckSheet |
Specify Other Document | QUALITY ALERT |
13. Effectiveness Of Action
Reviewed Quantity | 1 |
Reason for submission | ok |