QFR No - 8000852795
Defect Details
NC No. 8000852795
NC Date 24/11/2023
NC Submission Date
Part No. D3AD00500M
Part Name SHAFT CUT LENGTH (R122C MAXIMA Z)
Supplier Name & Code 101222-SANGKAJ ENGINEERING PVT LTD- U
ETL Plant 1152-ETL L-6/3/1DrivShaft
Defect Details DIAMETER OVER SIZE-OD O/S & SCRTCH MARK ON OD
 
1. Problem Description
Defect Description DIAMETER OVER SIZE-OD O/S & Taper & SCRTCH MARK ON OD - Shaft Maxima
Detection Stage Inprocess
Problem Severity Function
NG Quantity 514
Is Defect Repeatative? No
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID Irfan@sangkaj.com
Plant Head/CEO Email ID steel@sangkaj.com
MD Email ID anirudh.2007@hotmail.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
7000
0
0
1000
0
8000
Check Qty
4500
0
0
1000
0
5500
NG Qty
514
0
0
0
0
514
 
Scrap 0
Rework 514
Under Deviation 0
Containment Action
segregate pipe line material at ETL end & inhouse.
 
3. Process Flow
Process Flow Description
BAR CUTTING- TURNING -STRAIGHTENING-GRINDING- FINAL INSPECTION-PACKING-DISPATCH
 
4. Process Details
Process / Operation OD grinding
Outsource No
Machine / Cell Grinding m/c
Machine / Cell No. 1
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ManOD gauge not available.OD checked by micrometer as OD gauge given for calibration.X
MachineGrinding wheel wear outWheel Frequency not definedX
 
6. Inspection Method Analysis (Current)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection No
Checking Freq. 100%
Sampling No
Sample Size 100%
7. Root Cause Analysis (Occurance)
Why 1 DIAMETER OVER SIZE-OD O/S & SCRTCH MARK ON OD
Why 2 Grinding wheel wear out
Why 3 Grinding wheel dressing frequency not defined.
Why 4
Why 5
Root Cause (Occurance) Grinding wheel dressing frequency not defined.
 
Root Cause Analysis (Outflow)
Why 1 DIAMETER OVER SIZE-OD O/S & SCRTCH MARK ON OD
Why 2 OD Not checked by Gauge
Why 3 OD gauge given for calibration.
Why 4 Gauge calibration was due.
Why 5
Root Cause (Outflow) Gauge calibration was due.
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OutflowNew OD Snap gauge purchased, OD 100 % Check by snap gauge.Inspector25/11/202327/11/2023Completed
OccuranceGrinding wheel dressing frequency defined afteroperator25/11/202327/11/2023Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System No
Change Details OD check by snap gauge
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100 %
10. Evidance of Countermeasure
Occurance (Before) Grinding wheel dressing frequency not defined.
600_Occurance_Before.jpeg
Occurance (After) Grinding wheel dressing frequency defined .
600_Occurance_After.jpeg
Outflow (Before) OD checked by micrometer as OD gauge given for calibration.
600_Outflow_Before.jpeg
Outflow (After) New OD Snap gauge purchased, OD 100 % Check by snap gauge.
600_Outflow_After.jpeg
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant Machine,Man
 
12. Document Review
Documents ControlPlan, PFMEA
Specify Other Document G.wheel dress.Record
 
13. Effectiveness Of Action
Reviewed Quantity
Reason for submission