QFR No - 8000883655
Defect Details
NC No. 8000883655
NC Date 22/07/2024
NC Submission Date
Part No. B2BK02403O
Part Name CALIPER BODY-RAW K2 REAR (MODEL-B20013)
Supplier Name & Code 101180-MAULI CAST TECH PVT. LTD
ETL Plant 1120-ETL K-226/2 Disc Brakes
Defect Details BLOW HOLES-BH,PH, DENT & DAMAGEDON A CLASS AREA
 
1. Problem Description
Defect Description BLOW HOLES-BH,PH, DENT & DAMAGEDON A CLASS AREA
Detection Stage Inprocess
Problem Severity Aesthetic
NG Quantity 138
Is Defect Repeatative? No
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID quality@maulicasttech.com
Plant Head/CEO Email ID planthead@maulicasttech.com
MD Email ID shrikant.shelke@maulimetal.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
7101
0
0
336
1724
9161
Check Qty
7101
0
0
336
1724
9161
NG Qty
138
0
0
6
32
176
 
Scrap 7
Rework 31
Under Deviation 0
Containment Action
All remaining parts are being segregated at customer end. And in-house FG also all parts are rechecked & confirmed OK before dispatch.
 
3. Process Flow
Process Flow Description
1.Raw material received-->2.Incoming Inspection-->3.Storage-->4.Ingot Melting-->5.N2 Degassing Process-->6.Transfer to GDC Production-->7.Decoring-->8.Gate/Raiser Cutting-->9.Buffing-->10.Fettling-->11.Heat Treatment-->12.Shot Blasting--> 13.Engraving/Marking-->14.Final Inspection-->15.Packing & Move to FG-->16.PDIR Inspection-->17.Dispatch.
 
4. Process Details
Process / Operation At Post operation stage during cutting & fetlling.
Outsource No
Machine / Cell N/A
Machine / Cell No. N/A
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ManSemi skilled manpower, Less awareness about part handling process.Operator has changed,Less awareness of part handling process.X
ToolUse of improper tool.Not using standard tools.X
MethodMetal to metal contact,Using non-standard bins, shortage of bins.Part to part contact found,No standard bins for part handling,No sufficient bins for part movement.X
 
6. Inspection Method Analysis (Current)
Inspection Method Other
Other Inspection Method Visual inspection
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size Every lot
7. Root Cause Analysis (Occurance)
Why 1 Metal to metal contact during every operation.
Why 2 Due to not using standard bins.
Why 3 Due to some bins are got damaged.
Why 4 Due to put over load in bins.
Why 5 Due to lack of standard bins.
Root Cause (Occurance) Due to lack of standard & dedicated bins for part handling in every process. And operators are semi skilled.
 
Root Cause Analysis (Outflow)
Why 1 Avoid metal to metal contact during every operation.
Why 2 To be use standard bins for part handling.
Why 3 Don`t to be use damaged bins for carrying the parts.
Why 4 Put the parts in bins as per defined qty.
Why 5 To procure standard bins for proper part handling.
Root Cause (Outflow) Need to procure standard bins for every process & operations. And OJT need to provide all semi skilled operators.
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccuranceNow procured standard bins for part handling. And training has given to semi skilled operators.Mr.Somesh Rout & Debanand Mohapatra14/08/2024Completed
OutflowStandard bins are provided for part handling & operators trainingMr.Somesh Rout & Debanand Mohapatra14/08/2024Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details Q gate inspection activity has started before heat treatment process.
Inspection Method Other
Other Inspection Method Visual Inspection
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size Every lot
10. Evidance of Countermeasure
Occurance (Before) No standard & dedicated bins are there at post operation stage for part handling process.
961_Occurance_Before.jpeg
Occurance (After) Now standard & dedicated bins are procured for part handling.
961_Occurance_After.jpeg
Outflow (Before) Operators are not fully aware about the customer requirement.
961_Outflow_Before.jpeg
Outflow (After) Now provided training & awareness to operators about customer requirement.
961_Outflow_After.jpeg
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant Applicable to all rear caliper model family.
 
12. Document Review
Documents WISOP, AuditCheckSheet, ProcessFlowChart, PackingStd, InspCheckSheet
Specify Other Document N/A
 
13. Effectiveness Of Action
Reviewed Quantity 300
Reason for submission Material handling improved.