QFR No - 8000886620
Defect Details
NC No. 8000886620
NC Date 12/08/2024
NC Submission Date
Part No. F2LG05302B
Part Name SEAT PIPE - ABWB ENDURO
Supplier Name & Code 100539-N P ENTERPRISES
ETL Plant 1117-ETL K-228/9 Suspension
Defect Details NOT AS PER SPECIFICATION-OD OVER SIZE
 
1. Problem Description
Defect Description NOT AS PER SPECIFICATION-OD OVER SIZE
Detection Stage Inprocess
Problem Severity Fitment
NG Quantity 20
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID quality@npcindustries.in
Plant Head/CEO Email ID anand@npcindustries.in
MD Email ID ajay@npcindustries.in
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
960
3500
0
0
0
4460
Check Qty
960
3500
0
0
0
4460
NG Qty
20
50
0
0
0
70
 
Scrap 0
Rework 70
Under Deviation 0
Containment Action
100% inspection of Seat Pipes with fitment part
 
3. Process Flow
Process Flow Description
Process Flow Description 1.0 Raw Material 2.0 Cutting 3.0 Drawing 4.0 Head Formation 5.0 Rough Grinding 6.0 Punching 7.0 CNC Head Turning 8.0 CNC Boring & Facing 9.0 Tapping 10.0 Chamfering 11.0 ID Deburring 12.0 Finish Grinding 13.0 Final Inspection 14.0 Cleaning 15.0 Oiling 16.0 Packing &Dispatch.
 
4. Process Details
Process / Operation Finish Grinding
Outsource No
Machine / Cell Centerless Grinding Machine
Machine / Cell No. Grinding Section
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ToolGrinding wheel wearoutDuring defect simulation part made with wearout grinding wheel stem OD found oversize.X
MaterialMaterial Hardness moreMaterial hardness found to be within limitsO
ManIn Process Operator NegligentIn process operator was not found to be negligent .O
ToolWrong measuring instrument usedAs per Control Plan instrument is used for inspection.O
MethodLow lux levelLux level is within specified limit,920Lux.O
MethodInspection method inadequateDuring Gemba visit we found Inspection method inadequateX
 
6. Inspection Method Analysis (Current)
Inspection Method Instrument
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. Sampling
Sampling No
Sample Size As per std
7. Root Cause Analysis (Occurance)
Why 1 Stem OD Oversize
Why 2 Taper in OD
Why 3 Grinding Wheel wear out
Why 4 Grinding Wheel Dressing frequency inadequate
Why 5
Root Cause (Occurance) Grinding Wheel Dressing frequency inadequate
 
Root Cause Analysis (Outflow)
Why 1 Stem OD Oversize
Why 2 Defected part was Skipped at final inspection
Why 3 Could not be detected at final inspection
Why 4 Sampling qty was less
Why 5
Root Cause (Outflow) Sampling qty was less
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccuranceTraining to be given to operators for prevent from this type of defect.Mr. Gurpreet Singh15/08/202414/08/2024Completed
OutflowQ-alert to be displayed at Final Q-gate.Mr. Princ13/08/202412/08/2024Completed
OccuranceQ-alert to be displayed at final Grinding station.Mr. Princ13/08/202412/08/2024Completed
Outflow100% Inspection of stem OD to be done with Plain Ring Gauge .Mr. Vinay Tiwari20/08/202419/08/2024Completed
OccuranceDressing frequency of Grinding Wheel to be revised after proper validation (Before -125 pc to After validation-100pc) and to be followed strictly.Mr. Ankush20/08/202416/08/2024Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details 100% Inspection of stem OD to be started with Plain Ring Gauge .
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) Before Grinding dressing frequency was 125 pc
1011_Occurance_Before.jpg
Occurance (After) After Grinding dressing frequency is 100 pcs
1011_Occurance_After.jpg
Outflow (Before) Sampling Inspection of stem OD was done with micrometer.
1011_Outflow_Before.png
Outflow (After) 100% Inspection of stem OD to be started with Plain Ring Gauge .
1011_Outflow_After.jpg
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant All Similar model
 
12. Document Review
Documents ControlPlan, PFMEA, WISOP, InspCheckSheet
Specify Other Document No
 
13. Effectiveness Of Action
Reviewed Quantity 50
Reason for submission OK