Name of the Supplier | HI TECH ARAI PVT LTD UNIT XI(100865) |
Name of the Change Initiator | Canister machining process CNC to VMC |
Request Date | Jul 06, 2022 |
Proposal For | 1 |
Proposed Changes | Fixture change, Change of machine |
Process Route Change Details | |
Description of Proposed Change | Part change one process to another process orientation change so part handling issue avoid. Missing process identified in house. So implemented one step all Machining process. |
ETL Plant | Customer | Part No. | Proposed Saving |
---|---|---|---|
S21100507O |
Current Details (Before) | CNC OP #10 - Turning CNC OP#20- Grooving OP#30- Auto drilling & Pin pressing machining OP#40-Leak testing |
Trigger for the Change | Miss operation found in PDI Thread Ovality controlled Ovality observed Drilling & Reaming process |
Proposed Details (After) | OP#10- Grooving, Threading, Drilling,reaming |
Proposed Benefits of the Change | Quality Improvement, Manpower Reduction |
Current Status | Approved & Closed |
Status Updated By | |
Status Update Date |
Activity | Target Date | Responsibility | Status |
---|
File For | File Name |
---|---|
Reference File | View File |
Activity | Answer | Responsibility | ETL Remarks | Supplier's Remarks | Final Remarks | Status | Plant | Department |
---|
Role | Employee | Request Status | Comments | Updated On | Status |
---|