QFR No - 7000839800
Defect Details
NC No. 7000839800
NC Date 30/05/2022
NC Submission Date
Part No. C2PP00320B
Part Name WHEEL CLUTCH_C20009_D1
Supplier Name & Code 100432-BHAKTI AUTO COMP PRIVATE LIMIT
ETL Plant 1132-ETL K-226/1 TRANSMISSION
Defect Details PCD SHIFT-PCD GAUGE NOT QUALIFY
 
1. Problem Description
Defect Description Part are not qualifying to PCD gauge
Detection Stage Receipt
Problem Severity Fitment
NG Quantity 40
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID sales@bhaktiauto.com
Plant Head/CEO Email ID sales@bhaktiauto.com
MD Email ID vinodanin@gmail.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
300
0
0
500
0
800
Check Qty
300
0
0
500
0
800
NG Qty
1
0
0
1
0
2
 
Scrap 2
Rework 0
Under Deviation 0
Containment Action
100% Inspection at final inspection stage
 
3. Process Flow
Process Flow Description
Pressure Die casting-fettling-machining-Drilling-Tapping-Inspection-dispatch
 
4. Process Details
Process / Operation Drilling/Tapping
Outsource Yes
Machine / Cell VMC
Machine / Cell No. VMC cell
5. Problem Analysis
Type Possible Cause Fact Verification Jud
MethodPart Orientation of fixturePart orientation is at casting oil holeO
 
6. Inspection Method Analysis (Current)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
7. Root Cause Analysis (Occurance)
Why 1 PCD Not Ok
Why 2 Part not located properly on fixture
Why 3 part locating in on casting oil hole
Why 4 oil hole has more clearance
Why 5 Non precise parameter
Root Cause (Occurance) part not mounted properly in its position on fixture.
 
Root Cause Analysis (Outflow)
Why 1 PCD not ok
Why 2 part inspection missing
Why 3 final inspection not done
Why 4 sampling inspection
Why 5
Root Cause (Outflow) Sampling inspection hence part not detected in final inspection
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OutflowPCD inspection 100% to be done at final inspectionBhakti Auto01/06/202201/06/2022Completed
OccurancePart orientation locator to be changeOM Mahabali15/06/202215/06/2022Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details PCD gauge 100% inspection implemented instead of sampling
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) Pin Locator
157_Occurance_Before.pdf
Occurance (After) Spring mechanism locator
157_Occurance_After.pdf
Outflow (Before) Sampling Inspection
157_Outflow_Before.pdf
Outflow (After) 100% Inspection
157_Outflow_After.jpeg
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant No
 
12. Document Review
Documents ControlPlan
Specify Other Document x
 
13. Effectiveness Of Action
Reviewed Quantity 2000
Reason for submission OK