QFR No - 8000889503
Defect Details
NC No. 8000889503
NC Date 02/09/2024
NC Submission Date
Part No. F2GN11802B
Part Name MAIN SPRING-ABWB ENDURO
Supplier Name & Code 100952-STUMPP SCHUELE AND SOMAPPA SPR
ETL Plant 1117-ETL K-228/9 Suspension
Defect Details LENGTH OVERSIZE-TOTAL LENGTH OVERSIZE
 
1. Problem Description
Defect Description TOTAL LENGTH OVERSIZE
Detection Stage Inprocess
Problem Severity Function
NG Quantity 129
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID hravikumar@ssssprings.com
Plant Head/CEO Email ID sreenivasulu.k@ssssprings.com
MD Email ID rln@ssssprings.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
1500
0
0
300
0
1800
Check Qty
1500
0
0
300
0
1800
NG Qty
129
0
0
0
0
129
 
Scrap 129
Rework 0
Under Deviation 0
Containment Action
After Receipt of Complaint 100% Parts Verify at ETL End as Well as Inhouse for Length Undersize Issue, At ETL found 129 no`s Length Undersize spring
 
3. Process Flow
Process Flow Description
Coiling - Tempering-Grinding-Shot Peening - Setting-100% Lo Inspection-2nd Tempering-Visual Inspection-Oiling-Final Inspection-FG Storage-Packing-Dispatch
 
4. Process Details
Process / Operation Setting / Lo Inspection
Outsource No
Machine / Cell FF Cell
Machine / Cell No. 02
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ManOperator Verified only Part Name not Item CodeOperator not verified Properly Item CodeX
MethodAt Setting (Scragging) & Length Inspection Stage Improper Set-upOperator Set-up at Scragging Stage length as per Similar name ABWB ADJUSTABLE. instead of ABWBX
Method100% Length Operator Set Universal Snap Gauge as Per ABWB ADJS. (E92 Parts) and Checked LengthDue to Same Name- As per ABWB ADJS. Length inspection carried (ABWB ADJS. Length is less than ABWB )X
 
6. Inspection Method Analysis (Current)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
7. Root Cause Analysis (Occurance)
Why 1 Length Undersize Spring Observed
Why 2 At Setting (Scragging) Stage Improper Set-up
Why 3 Due to Similar name ABWB ADJUSTABLE. instead of ABWB Operator Set-up at Scragging Stage length as per ABWB Adjustable
Why 4 Operator less aware about Similar Model-As per Tag Name Mentioned only ABWB
Why 5 Due to this Length Undersize issue Happen
Root Cause (Occurance) Due to Similar name ABWB & ABWB Adjs. Operator Set-up Scragging as per ABWB Adjs.
 
Root Cause Analysis (Outflow)
Why 1 Length Undersize Spring Observed
Why 2 100% Length Operator Set Universal Snap Gauge as Per ABWB ADJS. (E92 Parts) and Checked Length
Why 3 Due to this Length Undersize issue observed
Why 4
Why 5
Root Cause (Outflow) 100% Length Operator Set Universal Snap Gauge as Per ABWB ADJS. (E92 Parts) and Checked Length- Due to Similar name
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccuranceSimilar Parts Lengthwise Matrix Made and Displayed on Scragging Stage - (As well Inform to Operator to verify as per Item Code )Mr. Ishwar Jadhav05/09/202401/09/2024Completed
OccuranceEarlier Universal Gauge Set -up with Vernier Caliper, Now We have Made Spring wise Limit Sample for Length Set-up, Operator Can Compare with Respective ModelMr. Shankar Fadat06/09/202406/09/2024Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System No
Change Details Earlier Universal Gauge Set -up with Vernier Caliper, Now We have Made Spring wise Limit Sample for Length Set-up, Operator Can Compare with Respective Model During Scragging Set-up
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) Due to Similar name ABWB & ABWB Adjs. Operator Set-up Scragging as per ABWB Adjs.
1060_Occurance_Before.pdf
Occurance (After) Similar Parts Lengthwise Matrix Made and Displayed on Scragging Stage - (As well Inform to Operator to verify as per Item Code )
1060_Occurance_After.pdf
Outflow (Before) 100% Length Operator Set Universal Snap Gauge as Per ABWB ADJS. (E92 Parts) and Checked Length- Due to Similar name
1060_Outflow_Before.pdf
Outflow (After) Earlier Universal Gauge Set -up with Vernier Caliper, Now We have Made Spring wise Limit Sample for Length Set-up, Operator Can Compare with Respective Model
1060_Outflow_After.pdf
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant FF Cell
 
12. Document Review
Documents WISOP
Specify Other Document Limit Sample
 
13. Effectiveness Of Action
Reviewed Quantity 50
Reason for submission ok