QFR No - 8000853852
Defect Details
NC No. 8000853852
NC Date 05/12/2023
NC Submission Date
Part No. F2HL00402B
Part Name OIL LOCK COLLAR (HMC-31/K38G)
Supplier Name & Code 100106-SHARP ENGINEERS.
ETL Plant 1146-ETL Suspension Narasapura
Defect Details MIX UP OTHER MODEL-NOT USING K0PG MODEL MIX UP AT SHARP END
 
1. Problem Description
Defect Description Wrong part received not using K0PG Model ( mix up at supplier end)
Detection Stage Inprocess
Problem Severity Fitment
NG Quantity 506
Is Defect Repeatative? No
Defect Sketch / Photo qg2jbwcoxguonu5m4n2rmvlw.gif
Supplier Communication Details
Quality Head Email ID quality@apw3.co.in
Plant Head/CEO Email ID kurund.ma@sharp-engineers.com
MD Email ID urkhandelwal@sharp-engineers.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
5000
0
0
5000
1000
11000
Check Qty
5000
0
0
5000
1000
11000
NG Qty
506
0
0
0
0
506
 
Scrap 0
Rework 506
Under Deviation 0
Containment Action
Segregation done at ETL plant and mix up part removed from OK parts.
 
3. Process Flow
Process Flow Description
10) RM Inward 20) RM Storage 30) Parting & Forming 40) Chamfering 50) OD grinding 60) Plating (Outsource) 70) Inward Inspection 80) Final Inspection 90) Pre-dispatch Inspection 100) Packing and forwarding .
 
4. Process Details
Process / Operation Packing and forwarding .
Outsource No
Machine / Cell NA
Machine / Cell No. NA
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ManUn-skilled OperatorStage wise skill matrix and operator license are evident as per F/HR/06O
MaterialIncorrect RM gradeThird part inspection verified for chemical composition and hardness testing as per requirement.O
MachineInadequate check Point in JH check sheetMonthly JH check sheet available on machine and all the check point is being checked and recorded asO
MethodPacker Working Method WrongKept 2 different type material togetherX
ToolTool worn outTool life for all the tool i.e. forming tool, drill, tap and insert are defined and recorded as perO
 
6. Inspection Method Analysis (Current)
Inspection Method Other
Other Inspection Method Transparent poly ba
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
7. Root Cause Analysis (Occurance)
Why 1 Wrong Part reached at ETL
Why 2 Two different part kept at same location.
Why 3 Packing was same.
Why 4 Not detected from outside.
Why 5 Transparent poly bag not in used.
Root Cause (Occurance) Transparent poly bag not in used at BSR stage.
 
Root Cause Analysis (Outflow)
Why 1 Wrong Part reached at ETL
Why 2 Incorrect material selection form BSR while dispatching.
Why 3 Person not aware about the part
Why 4 SOP & Analysis: Material handling of Finish Product being supplied to Endurance not displayed at BSR.
Why 5
Root Cause (Outflow) SOP & Analysis: Material handling of Finish Product being supplied to Endurance not displayed at BSR.
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OutflowSOP & Analysis: Material handling of Finish Product being supplied to Endurance displayed at BSR.Mr. Ganesh Mande12/12/202312/12/2023Completed
OccuranceTransparent poly bag are being used at BSR stage.Mr. Ganesh Mande11/12/202311/12/2023Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details 100% inspection before dispatch.
Inspection Method Other
Other Inspection Method Visually
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
10. Evidance of Countermeasure
Occurance (Before) Transparent poly bag not in used at BSR stage.
603_Occurance_Before.pptx
Occurance (After) Transparent poly bag are being used at BSR stage.
603_Occurance_After.pptx
Outflow (Before) SOP & Analysis: Material handling of Finish Product being supplied to Endurance not displayed at BSR.
603_Outflow_Before.pptx
Outflow (After) SOP & Analysis: Material handling of Finish Product being supplied to Endurance displayed at BSR.
603_Outflow_After.pptx
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant NA
 
12. Document Review
Documents ControlPlan, PFMEA, WISOP, PackingStd, InspCheckSheet
Specify Other Document NA
 
13. Effectiveness Of Action
Reviewed Quantity 5000
Reason for submission Reviewed next 10 lots verified no mix up issues found ok