QFR No - 8000873544
Defect Details
NC No. 8000873544
NC Date 06/05/2024
NC Submission Date
Part No. F2FQ00407B
Part Name HOLDER HANDLE UPPER P/C (XF-521)
Supplier Name & Code 201092-PRANEEL INDUSTRIES
ETL Plant 1117-ETL K-228/9 Suspension
Defect Details DAMAGES-CUT MARK
 
1. Problem Description
Defect Description CUT MARK
Detection Stage Receipt
Problem Severity Aesthetic
NG Quantity 11
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID quality@praneelgroup.com
Plant Head/CEO Email ID praneelindustries@rediiffmail.com
MD Email ID anilpatil@praneelgroup.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
100
0
0
100
0
200
Check Qty
100
0
0
100
0
200
NG Qty
12
0
0
0
0
12
 
Scrap 12
Rework 0
Under Deviation 0
Containment Action
All WIP checked at all end . Defective parts rejected.
 
3. Process Flow
Process Flow Description
Casting - powder coating - machining - final inspection - packing - dispatch
 
4. Process Details
Process / Operation machining
Outsource No
Machine / Cell 01
Machine / Cell No. 01
5. Problem Analysis
Type Possible Cause Fact Verification Jud
ManNo awareness to operator for packingnew operatorX
Methodpacking standard not okpacking standard not followedX
 
6. Inspection Method Analysis (Current)
Inspection Method Other
Other Inspection Method visual
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
7. Root Cause Analysis (Occurance)
Why 1 Dent / Damages on parts
Why 2 Dent / Damages while packing
Why 3 Without partition packing in bins
Why 4 Packing standard not followed
Why 5
Root Cause (Occurance) Packing standard not followed
 
Root Cause Analysis (Outflow)
Why 1 Dent / Damage observed during packing.
Why 2 Dent / Damage observed during dispatch.
Why 3
Why 4
Why 5
Root Cause (Outflow) packing operator was not aware of this.
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OutflowPacking Standard followed for avoided dent damage.suraj madhavi10/04/202410/04/2024Completed
OccurancePartition add to bins avoided metal to metal contact.Madhav gaikwad10/04/202410/04/2024Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System No
Change Details -
Inspection Method Other
Other Inspection Method visual
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) PACKING NOT OK, METAL TO METAL CONTACT.
795_Occurance_Before.pptx
Occurance (After) Partition add to bins avoided metal to metal contact.
795_Occurance_After.pptx
Outflow (Before) Skipped from final inspection
795_Outflow_Before.xlsx
Outflow (After) Training & awareness given to final inspector
795_Outflow_After.xlsx
 
11. Horizontal Deployment
Horizontal Deployment Required No
Applicable Machine / Model / Plant -
 
12. Document Review
Documents PackingStd
Specify Other Document Q-ALERT
 
13. Effectiveness Of Action
Reviewed Quantity 150
Reason for submission Found ok