QFR No - 8000862065
Defect Details
NC No. 8000862065
NC Date 07/02/2024
NC Submission Date
Part No. F2BZ05712B
Part Name CAP OIL LOCK - J1D FF (10mm taper)
Supplier Name & Code 101255-MAHAVIR INDUSTRIES
ETL Plant 1117-ETL K-228/9 Suspension
Defect Details NOT AS PER SPECIFICATION-PARELLELISM MORE
 
1. Problem Description
Defect Description Parallelism more
Detection Stage Inprocess
Problem Severity Function
NG Quantity 27
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID quality@mahavirind.co.in
Plant Head/CEO Email ID planthead@mahavirind.co.in
MD Email ID
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
2500
0
0
1580
0
4080
Check Qty
2500
0
0
1580
0
4080
NG Qty
27
0
0
2
0
29
 
Scrap 29
Rework 0
Under Deviation 0
Containment Action
All Stages +customer End All suspected Finish Good material Verified
 
3. Process Flow
Process Flow Description
R/M Inward - R/M Store- Traub parting (10.5 ID Hole - CNC Taper Turning/ ID Boring - Bottom Side Chamfer- OD Grinding- Rust preventive washing - Final Inspection - Packing- Dispatch.
 
4. Process Details
Process / Operation CNC Taper Turning/ ID Boring
Outsource No
Machine / Cell CNC-2
Machine / Cell No. CNC SECTION
5. Problem Analysis
Type Possible Cause Fact Verification Jud
MachineHeavy Burr Sticked With CNC Chuck JawAir Flushing Arrangement not available on CNC Machine.O
 
6. Inspection Method Analysis (Current)
Inspection Method Instrument
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
7. Root Cause Analysis (Occurance)
Why 1 Parallelism Not OK
Why 2 Job Not proper clam Feed at CNC Jaw
Why 3 Heavy Burr Sticked With jaw
Why 4 Air Flushing Arrangement not available on machine.
Why 5
Root Cause (Occurance) Heavy Burr Sticked With jaw and Air Flushing Arrangement not available on machine..
 
Root Cause Analysis (Outflow)
Why 1 Parallelism Not OK
Why 2 Parallelism Parameter Not check 100 % on machine
Why 3 Parallelism parameter checking instrument not available
Why 4
Why 5
Root Cause (Outflow) Parallelism parameter checking instrument not available
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccuranceAir Flushing Arrangement not available on machine.Maintenance Head / Production Head/Quality Head12/02/202412/02/2024Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details New Dial stand arrange on CNC machine
Inspection Method Instrument
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 100%
10. Evidance of Countermeasure
Occurance (Before) Before Air Flushing Arrangement Not Available on CNC Machine for CNC Jaw Loose Burr Remove after Process Part Unload
659_Occurance_Before.pptx
Occurance (After) Air Flushing Arrangement on CNC Machine for 100% CNC Jaw Loose Burr Remove after Process Part Unload and then New Part Load for Machining Process.
659_Occurance_After.pptx
Outflow (Before) Before Dial Stand not Available on CNC machine for 100% parallelism specification Inspection
659_Outflow_Before.pptx
Outflow (After) Dial Stand Provide on CNC machine for 100% parallelism speciation Inspection .
659_Outflow_After.pptx
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant All Cap Oil Lock
 
12. Document Review
Documents ControlPlan, PFMEA
Specify Other Document no
 
13. Effectiveness Of Action
Reviewed Quantity 286
Reason for submission Found ok