QFR No - 7000909764
Defect Details
NC No. 7000909764
NC Date 17/04/2023
NC Submission Date
Part No. B2RW00226O
Part Name PISTON ACTUATOR REGULAR 32.1 MM
Supplier Name & Code 100106-SHARP ENGINEERS.
ETL Plant 1156-ETL Disc Brake P'Nagar
Defect Details LENGTH UNDERSIZE-
 
1. Problem Description
Defect Description Length short issue
Detection Stage Receipt
Problem Severity Fitment
NG Quantity 54
Is Defect Repeatative? Yes
Defect Sketch / Photo
Supplier Communication Details
Quality Head Email ID quality@apw3.co.in
Plant Head/CEO Email ID kurund.ma@sharp-engineers.com
MD Email ID urkhandelwal@sharp-engineers.com
2. Stock Details & action taken for NG parts
Location ETL End Warehouse Transit Supplier FG Supplier WIP Total
Total Qty
5000
5000
0
2000
0
12000
Check Qty
5000
5000
0
0
0
10000
NG Qty
54
2
0
0
0
56
 
Scrap 0
Rework 56
Under Deviation 0
Containment Action
Segregation done immediately at ETL pipeline material and warehouse material.
 
3. Process Flow
Process Flow Description
10) RM Inward 20) Parting & Forming 30) Forming 40) Plating Process (Outsource) 50) Inward inspection 60) Storage 70) Final Inspection
 
4. Process Details
Process / Operation Forming Process
Outsource No
Machine / Cell Traub Section
Machine / Cell No. SE/SO/01
5. Problem Analysis
Type Possible Cause Fact Verification Jud
MaterialIncorrect RM gradeThird part inspection verified for chemical composition and hardness testing as per requirement.O
MethodPISTON ACTUATOR-MODIFIED checking by single ended snap gauge.Sampling basis inspection as per IS:2500 and inspection done by vernier caliper..X
ToolExcess use of forming tool/Tool worn out.Tool life monitoring as per defined frequency and record updatedO
MachineInadequate check Point in JH check sheetMonthly JH check sheet available on machine and all the check point is being checked and recorded asO
ManJudgment error While checkingMaster sample/ Limit sample provided for Checking at final as well as process stageO
 
6. Inspection Method Analysis (Current)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
7. Root Cause Analysis (Occurance)
Why 1 Wrong part Piston Actuator KHI (B2RW00326O) mix up with PISTON ACTUATOR-MODIFIED (B2RW00226O)
Why 2 Single packing stage for both piston and both parts look like almost same.
Why 3 Packing person inadequate knowledge and get confused while packing
Why 4 OPL and Q alert not displayed at packing and inspection stage.
Why 5
Root Cause (Occurance) Packing person inadequate knowledge of part and OPL Q alert not displayed at packing and inspection stage.
 
Root Cause Analysis (Outflow)
Why 1 PISTON ACTUATOR-MODIFIED (B2RW00226O) mix up with Piston Actuator KHI (B2RW00326O)
Why 2 Sampling basis inspection as per IS:2500 and checking done by vernier caliper.
Why 3 No 100% inspection for piston actuator modified (B2RW00226O)
Why 4 By system design
Why 5
Root Cause (Outflow) No 100% inspection for piston actuator modified (B2RW00226O)
 
8. Countermeasure ( Occurrence , Outflow & System side Actions )
Type Countermeasure Details Responsibility Target Date Actual Date Status
OccurancePacking stages are identified for PISTON ACTUATOR-MODIFIED (B2RW00226O) and packing is being done at two different stage for both the pistons and OPL displayed.Mr. Shaikh L.n.12/04/202312/04/2023Completed
OutflowOn job training given to packing person and inspectors , OPL and Q alert displayed at packing and inspection stage to avoid mix up issue, Standard SESG provided for inspection in place of digital vernier.Mr. MD ansari/Mrs. Jadhav12/04/202312/04/2023Completed
 
9. Inspection Method After Customer Complaint
Change In Inspection System Yes
Change Details 100% inspection by SESG (Single ended snap gauge)
Inspection Method Gauge
Other Inspection Method
Check Point at Final Inspection Yes
Checking Freq. 100%
Sampling No
Sample Size 1:1
10. Evidance of Countermeasure
Occurance (Before) Packing person inadequate knowledge of part and OPL Q alert not displayed at packing and inspection stage.
415_Occurance_Before.pptx
Occurance (After) Packing stages are identified for PISTON ACTUATOR-MODIFIED (B2RW00226O) and packing is being done at two different stage for both the pistons and OPL displayed.
415_Occurance_After.pptx
Outflow (Before) No 100% inspection for piston actuator modified (B2RW00226O) checking done by vernier caliper.
415_Outflow_Before.pptx
Outflow (After) On job training given to packing person and inspectors , OPL and Q alert displayed at packing and inspection stage to avoid mix up issue, Standard SESG provided for inspection in place of digital vernier.
415_Outflow_After.pptx
 
11. Horizontal Deployment
Horizontal Deployment Required Yes
Applicable Machine / Model / Plant NA
 
12. Document Review
Documents ControlPlan, PFMEA, WISOP
Specify Other Document NA
 
13. Effectiveness Of Action
Reviewed Quantity 100
Reason for submission ok